Defaulters Can’t Seek Enforcement Of Fundamental Rights: Supreme Court

The apex court refused to entertain a petition filed by real estate major Unitech.

Source: Supreme Court of India website
Source: Supreme Court of India website

Defaulters cannot be allowed to approach the apex court to get their fundamental rights enforced against the government and its authorities, the Supreme Court said on Monday.

The apex court refused to entertain a petition filed by embattled real estate major Unitech Ltd.

Unitech had filed a plea in apex court under Article 32 (right to move to Supreme Court for getting fundamental rights protected) seeking direction to Telangana State Industrial Infrastructure Corporation for the release of over Rs 165 crore pending with it.

“We cannot entertain a defaulter or grant him indulgence under Article 32 of the Constitution. We are not going to interfere with Article 32. You better move the High Court for the relief under Article 226 of Constitution,” a bench headed by Justice Dipak Misra said.

Senior advocate Kapil Sibal, appearing for the real estate major, said the firm did not have money to pay the flat buyers and if the directions are issued to Telangana state Industrial Infrastructure Corporation to refund the pending amount of over Rs 165 crore, then it would be of great help.

He said if the company moved the high court, it would consume lot of time and Unitech would not be able to meet the May 8 deadline fixed by apex court.

“We cannot collect money for you (Unitech). You have to pay the flat buyers for the delayed possession. It's our order and we know how to execute our orders,” a bench, which also comprised Justice A M Khanwilkar and M M Shantanagoudar, said.

The apex court granted permission to withdraw the petition and clarified that it has not expressed any view on the merit of the case.

On April 24, the apex court had directed Unitech to deposit 14 per cent interest on Rs 16.55 crore invested by 39 home buyers at its project in Gurugram by May 8.

It had warned the reality firm that failure to meet the deadline could invite attaching of realtor’s property and refused to grant more time to Unitech Residential Resorts Ltd., which had delayed handing over of flats to these home buyers.

The 39 home buyers had booked flats in Unitech's Vista housing project in Gurugram. They had sought a refund of their principal amount, totalling Rs 16.55 crore with interest, after the developer, which had promised to give the possession by 2012, delayed it.

The apex court had on February 20 had directed the developer to deposit 14 per cent interest on Rs 16.55 crore invested by these home buyers and had said that the interest would be calculated from January 1, 2010. It had asked the real estate major to deposit the amount with the apex court registry.

However, it had said that the issue of compensation would be deliberated upon later.

The court on January 12 had directed that Rs 2 crore deposited by Unitech with its registry as principal amount, be distributed among 39 home buyers.