U.K. Nuclear’s Future Left in Limbo as Investors Walk Away

Clouds Gather Over U.K. Nuclear as Another Project Fails

The cancellation of a British nuclear project heaped yet more pressure on the government to find a way to build the low-carbon power source that’s seen as a crucial part of the nation’s future energy mix.

Hitachi Ltd.’s decision to pull the plug on its long planned Wylfa project leaves Electricite de France SA alone in building new reactors in Britain. Whether any more are built hinges on the British government finding a finance model that’s palatable to investors.

How to pay for these costly pieces of infrastructure remains the biggest unanswered question for the sector. At the same time renewable energy costs have plunged and wind and solar farms can be built much quicker.

“Nuclear power stations are very large projects with lead times of over a decade before any revenues flow,” said Professor Rob Gross, director of the U.K. Energy Research Centre. “If an individual project costs 15 billion pounds ($19.5 billion) or more then it is not surprising that the pool of private investors is quite small.”

U.K. Nuclear’s Future Left in Limbo as Investors Walk Away

For its part, the government is reluctant to put taxpayer money on the line for companies that reap generous payouts, and executives find it difficult to put so much of their capital into single projects that may be delayed by years and run massively over budget.

Despite this the U.K. says it is still committed to large-scale new nuclear, beyond EDF’s Hinkley Point C. That project will now cost as much as 22.5 billion pounds, taking into account inflation, and the guaranteed price of power is significantly higher than the latest round of offshore wind projects.

Just three years ago, the government anticipated building 18 gigawatts of nuclear power stations to replace the old plants. Now EDF’s Sizewell C is left as the sole project most likely to be built.

U.K. Nuclear’s Future Left in Limbo as Investors Walk Away

As for the rest of the nuclear fleet, they’re aging and facing early closures that will see 4 plants disappear by March 2024. That will leave a generation gap that needs to be filled.

Losing nuclear probably wouldn’t pose a threat to the U.K.’s ability to generate enough power but it could make achieving net zero more difficult. The generation gap could be filled by gas, batteries or small modular reactors that can provide back-up to renewable energy and keep the lights on.

New nuclear was until a few years ago seen as a vital low-carbon way of supplementing renewables -- and as such a key part of the future energy mix envisioned in a net zero world.

“The U.K. cannot realistically reach its target of net zero emissions without nuclear power,” said Peter Bird, Managing Director at Berkeley Research Group.

What the U.K. does next on nuclear should become clear when the long-awaited government white paper is published next month that’ll spell out future plans for the sector. Separately, the results of a consultation looking at finance options are expected. While the so-called regulated asset base model garnered initial support, ministers are considering other options that could include taking a stake in projects.

It may be possible that another developer will take on the Welsh Wylfa site in future and the government has signaled that it’s looking into small modular reactors that will be cheaper to build and more flexible. But the concept is some way from being a mainstream option.

The future of nuclear is “entirely in the government’s hands,” said Jonathan Marshall, head of analysis at the Energy and Climate Intelligence Unit. If the government doesn’t deliver a financing model “that works, that will make the decision that we’ll have to get to net zero without nuclear.”

Britain’s Nuclear Projects

Project NameSize (GW)PartnersStatusComments
Hinkley Point C3.2EDF, CGNUnder constructionOn track to start generating 2025, costing 22.5 billion pounds. Construction financed by EDF. Government guaranteed price for power sold from plant.
Sizewell C3.2EDF, CGNWaiting for planning permissionReactor design based on Hinkley plant. EDF looking for ways to fund it without shouldering all the risk. It’s seeking to combine government and private funding. Aims for planning application early 2020. Construction due to start 2021. Electricity flows from 2031.
Bradwell2.3CGNEarly technical stagesSeeking government approval for a Chinese reactor design. China’s ownership of a major infrastructure project likely to be politically sensitive.
Wylfa2.9HitachiAbandoned on Sept. 16Hitachi pulled out of project after putting it on hold in 2019. Was due to start generating in mid-2020s.
Oldbury2.9HitachiShelved on Jan. 17Project in very early development stages. Site identified but no applications had been made for regulatory approvals.
Moorside3ToshibaShelved on Nov. 8Decision to halt project came after failed attempts by Toshiba to sell its stake. No financing agreement was in place with the government. Was due to start operating in 2025.